Thursday 19 February 2015

TIMELINE



19/07/14- Deposit
01/08/14- ICT received
27/08/14- Pre-Colour selection Walkthrough
04/09/14- Preliminary Plans Signing
17/09/14- Colour Selection
02/10/14- HIA/Building Contract Signed
26/11/14- Electrical Appointment
07/12/14- Land Registered
23/12/14- Land Settlement, Construction Loan Approved
05/01/15- Authority To Commence Construction Received
03/02/15- Contract Variation
07/02/15- Contract Variation

18/02/15- Contract Variation
23/02/15- Revised Plan received and signed
23/02/15- Plans submitted to the Developer
02/03/15- Contract Variation/Amended Engineering Design due to ZoI
03/03/15- DA approval received/CDC Lodgement
13/03/15- Received House Number from City Council, we're house number 5
18/03/15- ECNSW Application lodged
20/03/15- CDC approval received
23/03/15- Construction List
23/03/15- First Progress Payment (Deposit Stage)
25/03/15- Slab Supervisor assigned by MJH
01/04/15- Construction Site to File
02/04/15- Site Pegged
Site Peg


07/04/15- Site Cut
09/04/15- Site Piering
10/04/15- Plumbing
11/04/15- Waffle Pods, Mesh Delivery
13/04/15- Waffle Pods Laying
14/04/15- Slab

                                                                               SLAB
24/04/15- Progress Payment 2 (Slab)
05/05/15- Termites Barrier Installed
06/05/15- Frames Delivery
11/05/15- Framework started
14/05/15- Meter Box Installed
15/05/15- Framework Completed
16/05/15- Gutter and Fascia Completed
18/05/15- Bricks Delivered
18/05/15- Progress Payment 3 (Framework)
18/05/15- Scaffolding + Roofs delivery
26/05/15- Roof works starts
29/05/15- Roofs finished








The best is yet to come!!!!